LiveFlexible access (Circular 1/2024): connection with curtailable capacity
Exchange rate published: No — No published MW relief → months earlier
SourceBtMData GridPass
Flexibility only becomes bankable when a grid operator states, in writing, how much earlier service a site gets for dependable load relief. We track who is getting there.
CNMC / REE / DSOs
LiveFlexible access (Circular 1/2024): connection with curtailable capacity
Exchange rate published: No — No published MW relief → months earlier
SourceFingrid
In preparationNew grid-connection priority rules for large loads (in preparation)
Exchange rate published: No — Not yet
SourceTenneT
LiveNon-firm / time-bound transport rights
Exchange rate published: Partial — Access granted, no time-advance rate
SourceNESO / DNOs
LiveConnections reform + flexible (non-firm) connection offers
Exchange rate published: No — Queue position not priced against flexibility
SourceCRU / EirGrid
LiveLarge energy user connection policy (on-site / flexible requirements)
Exchange rate published: No
SourceBNetzA / TSOs
In preparationFlexible connection agreements and controllable loads (EnWG)
Exchange rate published: No
SourceElia
LiveFlexible access for new grid users
Exchange rate published: No
SourceTerna / ARERA
LiveUVAM demand-side aggregation and interruptible loads in dispatch services
Exchange rate published: No — Market flexibility exists; not linked to earlier connection
SourceLast reviewed 2026-10-07. Summaries are indicative; confirm terms with the operator before relying on them.